Plannings

Paldiski LNG terminal general planning

20.01.2010 Initiation of general planning (available in Estonian)

26.02.2010 Public showing of EIA

26.02.2010 Public showing of general planning sketch (available in Estonian)

16.03.2010 Public consultation of general planning sketch and EIA program

22.06.2010 Public showing of EIA report

16.07.2010 Public consultation of EIA report

22.12.2011 Adoption of general planning (available in Estonian)

30.12.2011 – 27.01.2012 Public showing of general planning

31.01.2012 Public consultation of general planning (available in Estonian)

27.09.2012 Imposing of general planning (available in Estonian)

Paldiski LNG terminal mainland detailed planning

EIA was not initiated

01.10.2012 Initiation of detailed planning (available in Estonian)

07.10.2013 Adoption of detailed planning (available in Estonian)

04.11.2013 – 04.12.2013 Public showing of detailed planning

30.12.2013 Public consultation of detailed planning

22.05.2014 Imposing of detailed planning (available in Estonian)

Paldiski LNG terminal off-shore Environmental Impact Assessment
20.04.2014 – 17.05.2015 Public showing of EIA
20.05.2015 Public consultation of EIA